Type of approval | Approving Authority | Stage of project | Duration (Days) |
Building Permit Issue (All NOCs) | Municipal Authority | Pre-construction | 30 (60 days for High Rise and Tall buildings) |
Building Use Certificate | Municipal Authority | Post construction | 15 days for selfuse homes & 30 Days for other buildings. |