Timelines

Type of approval Approving Authority Stage of projectDuration (Days)
Building Permit Issue (All NOCs) Municipal Authority Pre-construction 30 (60 days for High Rise and Tall buildings)
Building Use Certificate Municipal Authority Post construction 15 days for selfuse homes & 30 Days for other buildings.